Testing showed the aging power feeds and main switch gear at the court and county buildings are failing; a $202,000 design amendment plans a complicated replacement coordinated with DTE, while a new generator and transformer will be bid separately.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 20, 2026.
Impact analysis
$202,000 design amendment, from the 2026 Capital Improvement Plan.