Central Intake & Assessment Center / Jail Construction Change Orders

Macomb County

Summary

The committees recommended nearly $1.7 million in contracts to furnish and equip the new Central Intake & Assessment Center, plus a security systems change order. The project remains on budget.

At a glance

Total mentions
8
Last 30 days
1

Discussed at 2 meetings in the last 60 days; most recently Oct 22, 2026.

Impact analysis

💰Financial impact

About $1.7 million in new contracts, all within the existing CIAC project budget.

✅Who benefits

The sheriff's office and residents going through the county's intake and assessment system.

⚠️Who could be affected

If the allegations hold, the county faces liability and safety risk at a 24/7 detention facility.

Mentions & discussions (8)

MeetingOct 22, 2026approved

Board of Commissioners - Full Board - Oct 22, 2026

The board approved millions in contracts to furnish and equip the county's new Central Intake & Assessment Center, a major piece of the jail/community services campus.

MeetingOct 6, 2026approved

Board of Commissioners - Joint Finance/Audit/Budget and Internal Services Committees - Oct 6, 2026

The committees recommended nearly $1.7 million in contracts to furnish and equip the new Central Intake & Assessment Center, plus a security systems change order. The project remains on budget.

MeetingAug 10, 2026approved

Board of Commissioners - Joint Finance/Audit/Budget and Internal Services Committees - Aug 10, 2026

The county's new intake and assessment facility is on time and under budget, with construction moving through mechanical, electrical and finishing work. A national corrections-industry magazine even featured the project as a model for other counties. ARPA funding deadlines remain on track.

MeetingJun 11, 2026

Board of Commissioners - Full Board - Jun 11, 2026

A union glazier told commissioners the jail intake facility's glass curtain wall was installed with quarter-inch light-duty screws instead of half-inch structural bolts — a roughly 90% strength shortfall. Four commissioners voted against a related design amendment until an independent inspection happens, and the chair says the issue will be raised Tuesday.

MeetingMar 26, 2026approved

Board of Commissioners - Full Board - Mar 26, 2026

The county added about $3.5 million in change orders to the intake center/jail project, including $3 million for cabling and mechanical work. The project now runs to March 2027.

MeetingMar 19, 2026

Board of Commissioners - Joint Public Services and Records and Public Safety Committees - Mar 19, 2026

Two new Community Mental Health therapists, paid entirely from opioid settlement funds, will start screening inmates for mental health and substance-use needs at the Central Intake and Assessment Center before it opens in 2027 — building the data needed to staff and program the facility properly.

MeetingMar 18, 2026

Board of Commissioners - Joint Finance/Audit/Budget and Internal Services Committees - Mar 18, 2026

The county approved three change orders with Granger Construction worth about $3.5 million for the jail and intake center project. The largest piece — $2.47 million of structured cabling — is money moved from the technology budget, not a project cost increase.

MeetingFeb 11, 2026

Board of Commissioners - Joint Finance/Audit/Budget and Internal Services Committees - Feb 11, 2026

The county's ~$230 million jail and assessment center project is on time and on budget, with about 90% of commitments bought out and $9.2 million in contingency remaining. Precast construction is rising and three of four demolition wings are done, with opening expected in 2027.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Macomb County

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.