Administration Building Plaza Deck Deterioration
Macomb County
Summary
The plaza deck over the Administration Building's underground garage has leaked for a decade, and excavations revealed steel deterioration bad enough to pose a structural failure risk — the area is cordoned off and emergency shoring is underway. The committee approved an extra $750,000, with more possibly coming this winter.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 20, 2026.
Impact analysis
An extra $750,000 was approved now, with a phase-two garage project and possibly more funding requests expected.
County employees and residents who use the Administration Building and its underground garage get a safer, watertight structure.
Mentions & discussions (2)
Board of Commissioners - Finance/Audit/Budget Committee - Oct 20, 2026
The plaza deck over the Administration Building's underground garage has leaked for a decade, and excavations revealed steel deterioration bad enough to pose a structural failure risk — the area is cordoned off and emergency shoring is underway. The committee approved an extra $750,000, with more possibly coming this winter.
Board of Commissioners - Full Board - Jul 23, 2026
The county is spending $1.557 million to waterproof the Phase 1 plaza deck at the Mount Clemens Administration Building.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Macomb County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.